Facilities
8
AI Workload Focus
AI data centers focused on HPC / Supercomputing workloads — where operators are building and at what scale. 8 facilities with 403.1 MW of selected tracked capacity.
Facilities
8
Tracked Capacity
403.1 MW
Operators
13
Countries
8
Operational
5
Market Composition
Status, operator concentration, and energy profile across 8 facilities.
| Facility | Operator | Location | Capacity ↓ | Status | Energy | Workload | Readiness | Sources |
|---|---|---|---|---|---|---|---|---|
| ODATA (Aligned Data Centers) | Colombia Cundinamarca | 120 MW | under construction | Other | HPC / Supercomputing | 1 | ||
| Microsoft | Poland Masovian | 100 MW | under construction | Other | HPC / Supercomputing | 1 | ||
| Foxconn (Hon Hai Technology Group) & NVIDIA | Taiwan Kaohsiung | 100 MW | under construction | Other | HPC / Supercomputing | 1 | ||
| Green Mountain ASHewlett Packard Enterprise | Norway Vestfold og Telemark | 50 MW | operational | Renewable | HPC / Supercomputing | 2 | ||
| Forschungszentrum JülichEuroHPC JUEviden (Atos)NVIDIA | Germany North Rhine-Westphalia | 10 MW | operational | Renewable | HPC / Supercomputing | 2 | ||
| Barcelona Supercomputing CenterEuroHPC JULenovo | Spain Catalonia | 10 MW | operational | Other | HPC / Supercomputing | 2 | ||
| CSC – IT Center for ScienceEuroHPC JUHewlett Packard Enterprise | Finland Kainuu | 7 MW | operational | Renewable | HPC / Supercomputing | 2 | ||
| CINECAEuroHPC JUEviden (Atos) | Italy Emilia-Romagna | 6 MW | operational | Renewable | HPC / Supercomputing | 2 |