AI data center dossier
Country
Brazil
Operator
Scala Data Centers
Energy
Renewable
Tracked capacity
4.8 GW
Campus power envelope | Primary source
4.75 GW is the planned Scala AI City full-build campus capacity; the related MME authorization is a 5 GW grid connection.
Evidence profile
Readiness reflects whether the record has citations, narrative context, structured power data, coordinates, and at least one dated milestone.
Readiness
100%
3 citations linked
-30.003, -51.301
Campus power envelope | Primary source
2 dated fields available
HTML, JSON, and GeoJSON all available
Machine-readable outputs
Canonical record surfaces for audit, programmatic use, and direct citation.
Scala AI City is a planned gigawatt-scale data-center campus in Eldorado do Sul, Rio Grande do Sul. Scala announced the project with the Rio Grande do Sul government in 2024, describing a first phase of 54 MW and potential full development to 4.75 GW. In May 2025, Scala announced that Brazil's Ministry of Mines and Energy authorized a 5 GW ramp-up connection for Scala AI City to the National Interconnected System, and said the fully built campus would have 4.75 GW of capacity. ADCI changes the record from operational to planned because opened sources support a planned campus and energy authorization, not a fully operational 4.75 GW facility. The selected 4,750 MW value is the planned full-build campus power envelope tied to the authorized grid connection, not current IT load.
No obvious coverage gaps detected in the current structured record.
Structured analysis covering this facility's operator and market context.