| O'Leary VenturesMunicipal District of Greenview | Canada Western Canada | 7,500 MW | planned full-build campus; Phase 1 power infrastructure proposed | Gas | Mixed | | 5 |
| MetaEntergy Louisiana | United States Richland Parish, Louisiana | 5,000 MW | under construction; future 5 GW expansion not yet delivered | Nuclear | Training | | 4 |
| Scala Data Centers | Brazil Rio Grande do Sul | 4,750 MW | planned campus with 5 GW grid-connection authorization and 54 MW first phase disclosed | Renewable | Mixed | | 3 |
| MicrosoftNVIDIA | United States Mount Pleasant, Wisconsin | 3,300 MW | startup activity and equipment bring-up reported in May 2026; full campus buildout not complete | Other | Training | | 4 |
| xAI | United States Greater Memphis / Southaven xAI region | 2,000 MW | Colossus operational; Southaven MACROHARDRR expansion and power context still developing | Gas | Training | | 5 |
| ExxonMobil | United States United States | 1,500 MW | FEED-stage data-center power-generation initiative; customer and site not publicly disclosed | Gas | General Cloud | | 2 |
| Constellation EnergyMicrosoft | United States Londonderry Township / Middletown, Pennsylvania | 835 MW | planned 2028 restart pending regulatory approvals | Nuclear | Power-Linked AI Infrastructure | | 3 |
| Microsoft | Brazil São Paulo | 500 MW | operational | Renewable | Inference | | 1 |
| Microsoft | Japan Tokyo & Osaka | 500 MW | operational | Renewable | Mixed | | 1 |
| Oracle | Malaysia Greater Kuala Lumpur | 500 MW | planned | Mixed | Mixed | | 1 |
| Microsoft | Mexico Querétaro | 345 MW | operational | Mixed | Mixed | | 2 |
| Amazon Web Services | Brazil São Paulo | 300 MW | operational | Renewable | Mixed | | 2 |
| Amazon Web Services | Malaysia Greater Kuala Lumpur | 300 MW | operational | Renewable | Mixed | | 2 |
| Microsoft | Malaysia Greater Kuala Lumpur / Johor | 300 MW | operational | Mixed | Mixed | | 1 |
| Google | Malaysia Johor Bahru, Malaysia | 220 MW | under construction | Renewable | Mixed | | 1 |
| Apple | United States Multi-site (North Carolina, Oregon, Arizona) | 200 MW | operational | Renewable | Inference | | 2 |
| Microsoft | Indonesia Jakarta | 200 MW | planned | Mixed | Mixed | | 1 |
| CoreWeave | United Kingdom Greater London and Manchester | 150 MW | operational | Renewable | Mixed | | 1 |
| Microsoft | Austria Vienna | 120 MW | operational | Renewable | Inference | | 1 |
| Google | Thailand Chonburi Province | 100 MW | planned | Renewable | Mixed | | 2 |
| Microsoft | Thailand Eastern Economic Corridor (EEC) | 100 MW | planned | Mixed | Mixed | | 1 |
| ByteDanceVolcengine | China Inner Mongolia | 100 MW | construction started in November 2024, with Phase 1 planned for delivery from December 2025 | Other | AI & Cloud Infrastructure | | 4 |
| Microsoft | Colombia Cundinamarca | 80 MW | operational | Mixed | Azure AI services, Latin American enterprise AI workloads | | 1 |
| Google | South Africa Gauteng | 60 MW | operational | Mixed | Mixed | | 2 |
| Google | Philippines Metro Manila | 60 MW | operational | Mixed | General Cloud | | 1 |
| Microsoft | Austria Vienna | 60 MW | operational | Renewable | Inference | | 2 |
| Oracle | Greece Attica | 60 MW | operational | Mixed | General Cloud | | 1 |
| AI71G42Abu Dhabi Investment Authority | United Arab Emirates Abu Dhabi | 50 MW | operational | Mixed | Inference | | 2 |
| CyberportHKSAR GovernmentNVIDIA (Hardware partner) | Hong Kong Hong Kong Island | 50 MW | operational | Other | Mixed | | 2 |
| ByteDanceTikTok | Norway Hamar | 50 MW | under construction | Renewable | Inference | | 2 |
| King Abdullah University of Science and Technology (KAUST)Hewlett Packard Enterprise | Saudi Arabia Makkah | 35 MW | operational | Mixed | Research | | 2 |
| OoredooSyntysNVIDIA | Qatar Doha | 30 MW | operational | Other | Mixed | | 2 |
| Lawrence Livermore National LaboratoryHewlett Packard EnterpriseAMD | United States California | 30 MW | operational | Other | Training | | 6 |
| Government of EgyptMCIT | Egypt Cairo | 25 MW | operational | Other | Government AI & Analytics | | 2 |
| SDS (Shonfeld Data Services)VAST DataNVIDIA | Israel Petah Tikva | 18 MW | operational | Other | Mixed | | 2 |
| Oman Data ParkOmantelNVIDIA | Oman Muscat | 10 MW | operational | Other | Mixed | | 2 |
| Aqaba Digital Hub | Jordan Aqaba | 6 MW | operational | Other | Colocation & AI-ready infrastructure | | 2 |
| Amazon Web ServicesTalen Energy | United States Salem Township / Berwick, Pennsylvania | — | existing Susquehanna-adjacent AWS data-center campus with broader front-of-the-meter transition | Other | AI & Cloud Infrastructure | | 5 |
| Amazon Web Services | United States Madison County, Mississippi | — | Canton operating and Ridgeland in early construction as of June 2026; combined Madison County AWS data-center complexes still developing | Renewable | Mixed | | 5 |
| Amazon Web Services | United States Eastern Oregon | — | planned / land-use-approved regional expansion; individual project construction status varies and is not selected | Renewable | Unknown | | 10 |
| Pacific Gas and Electric Company (PG&E)Atomic CanyonNVIDIA | United States Avila Beach, California | — | AI document-search deployment at operating nuclear plant; no data-center capacity claim | Nuclear | Operations | | 2 |
| Google | United States Indiana | — | reported operational in December 2025; expansion and site work continue | Other | Mixed | | 8 |
| Google | United States Iowa-Nebraska cluster | — | regional Google data-center footprint with ongoing expansion | Renewable | AI & Cloud Infrastructure | | 5 |
| OpenAI | France Paris Region | — | announced office / infrastructure watch; no verified French data-center capacity | Other | Unknown | | 3 |