State Market

Georgia

AI data center buildout inside Georgia — operators, scale, and pipeline status. 4 facilities with 1.1 GW of selected tracked capacity.

Facilities

4

Tracked Capacity

1.1 GW

Operators

6

Statuses

3

Operational

1

Data Quality

100% cited
50% capacity published
50% geolocated
75% dated

Market Composition

How this slice breaks down

Status, operator concentration, and energy profile across 4 facilities.

Status distribution

Under construction125%

Energy mix

Other / Unknown4100%

Frequently asked questions

How many AI data centers are tracked for Georgia?
The AI Data Center Index tracks 4 facilities for Georgia with 1.1 GW of selected tracked capacity.

Facilities

Facility Operator Location Capacity ↓ Status Energy Workload Readiness Sources
PrologisAtlas DevelopmentUnited States
Georgia
900 MWrezoning approved; construction start and tenant not confirmedOtherAI & Cloud Infrastructure
4
DC BLOXUnited States
Georgia
216 MWunder constructionOtherInference
1
Digital RealtyTaurus DC SPE LLCUnited States
Stilesboro / Bartow County, Georgia
planned; rezoning/land-use approval recorded June 2025OtherUnknown
4
MicrosoftUnited States
Atlanta, Georgia
Microsoft says the Atlanta AI datacenter began operation in October 2025.OtherAI Training and Inference
3