| MetaEntergy Louisiana | United States Richland Parish, Louisiana | 5,000 MW | under construction; future 5 GW expansion not yet delivered | Nuclear | Training | | 4 |
| MicrosoftNVIDIA | United States Mount Pleasant, Wisconsin | 3,300 MW | startup activity and equipment bring-up reported in May 2026; full campus buildout not complete | Other | Training | | 4 |
| MetaVistra Corp | United States PJM grid region (Ohio and Pennsylvania) | 2,609 MW | 20-year Meta-Vistra nuclear PPAs announced January 2026; uprate capacity expected in early 2030s | Nuclear | Mixed | | 3 |
| Amazon Web Services | United States Oregon | 2,435 MW | operational AWS US West (Oregon) region and market footprint | Renewable | AI & Cloud Infrastructure | | 4 |
| Amazon Web ServicesAnthropic | United States New Carlisle, Indiana | 2,200 MW | operational first Project Rainier cluster; full campus buildout ongoing | Other | Mixed | | 4 |
| xAI | United States Greater Memphis / Southaven xAI region | 2,000 MW | Colossus operational; Southaven MACROHARDRR expansion and power context still developing | Gas | Training | | 5 |
| Amazon Web ServicesTalen Energy | United States Pennsylvania | 1,920 MW | under construction at Susquehanna-adjacent campus with additional planned Pennsylvania campuses | Nuclear | Mixed | | 5 |
| ExxonMobil | United States United States | 1,500 MW | FEED-stage data-center power-generation initiative; customer and site not publicly disclosed | Gas | General Cloud | | 2 |
| Vantage Data Centers | United States Shackelford County, Texas | 1,400 MW | construction began before August 2025 announcement; first building scheduled for H2 2026 | Other | Training | | 4 |
| MetaOklo Inc. | United States Pike County, Ohio | 1,200 MW | agreement announced January 2026; pre-construction and site characterization slated for 2026 | Nuclear | Training | | 2 |
| OpenAIOracleCrusoeLanciumNVIDIA | United States Abilene, Texas | 1,200 MW | first phase live; full 1.2 GW campus under construction | Gas | Mixed | | 4 |
| Amazon Web ServicesVistra Corp | United States Hood and Somervell Counties, Texas | 1,200 MW | planned data-center campus / contracted power delivery beginning Q4 2027 | Nuclear | Mixed | | 5 |
| Meta | United States El Paso, Texas | 1,000 MW | under construction; Meta says the site broke ground in 2025 | Renewable | AI Training and Inference | | 3 |
| Meta | United States Lebanon, Indiana | 1,000 MW | breaking ground announced February 2026 | Other | AI Training and Inference | | 1 |
| Meta | United States New Albany, Ohio | 1,000 MW | New Albany campus active and expanding; Prometheus described as a gigawatt-scale 2026 AI supercluster buildout | Nuclear | Training | | 5 |
| Vantage Data CentersOpenAIOracle | United States Port Washington, Wisconsin | 902 MW | groundbreaking reported December 2025; scheduled for completion in 2028 | Renewable | AI Training and Inference | | 3 |
| PrologisAtlas Development | United States Georgia | 900 MW | rezoning approved; construction start and tenant not confirmed | Other | AI & Cloud Infrastructure | | 4 |
| Constellation EnergyMicrosoft | United States Londonderry Township / Middletown, Pennsylvania | 835 MW | planned 2028 restart pending regulatory approvals | Nuclear | Power-Linked AI Infrastructure | | 3 |
| Amazon Web Services | United States Caroline and Spotsylvania Counties, Virginia | 770 MW | planned permit-stage campus | Other | AI workload not disclosed at facility level | | 3 |
| MetaTerraPower | United States United States | 690 MW | commercial agreement with initial delivery as early as 2032; specific initial dual-unit site not yet identified | Nuclear | AI power procurement | | 3 |
| NextEra EnergyGoogleCentral Iowa Power Cooperative | United States Palo / Linn County, Iowa | 615 MW | Duane Arnold restart targeted for full operation by Q1 2029, pending regulatory approvals. | Nuclear | AI power procurement | | 3 |
| Google | United States Pine Island, Minnesota | 600 MW | announced | Other | Mixed | | 1 |
| Google | United States Oklahoma | 600 MW | operational | Renewable | General Cloud | | 3 |
| Amazon Web Services | United States Ohio | 500 MW | operational | Renewable | Mixed | | 2 |
| Google | United States Iowa | 500 MW | operational | Renewable | Mixed | | 2 |
| GoogleKairos Power | United States United States | 500 MW | announced | Nuclear | Unknown | | 2 |
| Meta | United States Utah | 500 MW | under construction | Renewable | Training | | 2 |
| Microsoft | United States Arizona | 500 MW | operational | Renewable | Mixed | | 3 |
| Microsoft | United States Washington State | 500 MW | operational | Renewable | Mixed | | 2 |
| Tesla | United States New York | 500 MW | operational | Mixed | Training | | 3 |
| Applied DigitalCoreWeave | United States North Dakota | 400 MW | staged campus under construction | Renewable | Mixed | | 2 |
| Google | United States Oregon | 400 MW | operational | Renewable | Mixed | | 2 |
| Google | United States South Carolina | 350 MW | operational | Renewable | Mixed | | 2 |
| Meta | United States Iowa | 350 MW | operational | Renewable | Training | | 2 |
| Meta | United States Texas | 350 MW | operational | Renewable | Training | | 2 |
| Meta | United States Nebraska | 300 MW | operational | Renewable | Mixed | | 3 |
| Meta | United States Oregon | 300 MW | operational | Renewable | Inference | | 2 |
| Microsoft | United States Texas | 300 MW | operational | Renewable | Mixed | | 2 |
| Meta | United States Alabama | 227 MW | under construction | Renewable | Mixed | | 1 |
| Vantage Data Centers | United States Clark County, Nevada | 224 MW | under construction | Other | Mixed | | 1 |
| DC BLOX | United States Georgia | 216 MW | under construction | Other | Inference | | 1 |
| Apple | United States Multi-site (North Carolina, Oregon, Arizona) | 200 MW | operational | Renewable | Inference | | 2 |
| Apple | United States North Carolina | 200 MW | operational | Renewable | Mixed | | 3 |
| Meta | United States North Carolina | 200 MW | operational | Renewable | Mixed | | 2 |
| Vantage Data Centers | United States California | 200 MW | operational | Renewable | Mixed | | 2 |
| Google | United States Nevada | 150 MW | operational | Renewable | Inference | | 2 |
| Lambda Labs | United States Multi-site (Texas, Washington, Montana) | 150 MW | operational | Mixed | Mixed | | 2 |
| Apple | United States Oregon | 120 MW | operational | Renewable | Mixed | | 2 |
| Equinix | United States Silicon Valley | 117 MW | planned | Renewable | General Cloud | | 1 |
| Crusoe Energy Systems | United States Colorado | 100 MW | operational | Mixed | Mixed | | 3 |