Timeline Feed

Under Construction AI Data Center Feed

Chronological feed for Under Construction using the best public timeline year available for each tracked facility.

How to Use This Feed

Feed items are ordered by the strongest public timeline year available for each tracked facility. Use the HTML page for scanning and the XML endpoint for readers, alerting, or downstream tooling.

Chronological Entries

G42 “Stargate” UAE–US AI Campus (Abu Dhabi)
Abu Dhabi, Abu Dhabi, United Arab Emirates
2026
Under Construction5.0 GW

The UAE-US AI Campus is a 5 GW Abu Dhabi AI infrastructure campus led by G42 with U.S. technology partners. G42's May 2025 announcement says a new 5 GW UAE-US AI Campus was unveiled as the largest AI infrastructure project outside the U.S.

Data Center Valley Ekibastuz AI Campus
Ekibastuz, Pavlodar Region, Kazakhstan
2026
Under Construction1.0 GW

Kazakhstan's Prime Minister's office describes Data Center Valley in Ekibastuz, Pavlodar Region, as a state-backed project to create the largest data-center campus in Central Asia with energy capacity up to 1 GW. The government says 1,400 h

Google / AdaniConneX Visakhapatnam AI Hub
Visakhapatnam, Andhra Pradesh / Visakhapatnam, India
2026
Under Construction1.0 GW

Google / AdaniConneX Visakhapatnam AI Hub is a source-backed gigawatt-scale AI infrastructure project in Andhra Pradesh. Google Cloud's April 28, 2026 release says Google broke ground on the AI hub in Visakhapatnam, with the ceremony at Tar

Meta Lebanon AI Data Center
Lebanon, Lebanon, Indiana, United States
2026
Under Construction1.0 GW

Meta announced in February 2026 that it is breaking ground on a new data center campus in Lebanon, Indiana, one of its largest infrastructure investments to date. Meta says the data center is designed to deliver 1 GW of capacity once operat

Microsoft India South Central Cloud Region Program
Hyderabad / India South Central cloud-region program, India
2026
Under Construction600 MW

Microsoft India South Central Cloud Region Program tracks the Hyderabad-centered Microsoft cloud and AI infrastructure buildout, not a single mapped Hyderabad/Pune facility. Microsoft's December 9, 2025 release says the company will invest

SoftBank Tomakomai AI Data Center (Japan)
Tomakomai, Tomakomai, Hokkaido, Japan
2026
Under Construction300 MW

SoftBank is developing what is slated to be Japan’s largest AI data center in Tomakomai, Hokkaido. Announced in partnership with NVIDIA in November 2024, the facility will be the first in the world to receive NVIDIA DGX B200 systems (Blackw

Humain AI Data Centers (Saudi Arabia)
Riyadh, Riyadh & Dammam, Saudi Arabia
2026
Under Construction200 MW

Saudi Arabia's Public Investment Fund (PIF) created Humain in 2025 as the kingdom's national AI infrastructure company, tasked with building sovereign AI compute at a scale that positions Saudi Arabia as a global AI leader. Construction bro

Yotta D2 / NVIDIA Blackwell AI Supercluster (Greater Noida)
Greater Noida, Uttar Pradesh / Greater Noida, India
2026
Under Construction60 MW

Yotta D2 / NVIDIA Blackwell AI Supercluster is a planned high-density AI deployment at Yotta's 60 MW D2 data center in the Greater Noida hyperscale campus. Yotta's February 18, 2026 release says the supercluster will deploy 20,736 liquid-co

Equinix DA12 Dallas (Texas)
Dallas, Dallas, United States
2026
Under Construction40 MW

Equinix DA12 is a new International Business Exchange™ (IBX) data center in Dallas, Texas, representing a total investment of $835 million. The 372,517-square-foot facility is specifically designed for the high-density cooling requirements

Google Wilbarger County Data Center
Wilbarger County, Texas, United States
2026
Under Construction

Google announced a new data center under construction in Wilbarger County, Texas. Google's official Wilbarger County announcement says the facility will use advanced air-cooling technology, limiting water consumption to critical campus oper

OpenAI / G42 Stargate UAE Cluster
Abu Dhabi, Abu Dhabi, United Arab Emirates
2026
Under Construction

Stargate UAE is the OpenAI/G42/Oracle AI infrastructure cluster inside the larger UAE-US AI Campus in Abu Dhabi. OpenAI says the partnership includes a 1 GW Stargate UAE cluster, with 200 MW expected to go live in 2026. G42 likewise describ

AWS Pennsylvania AI Innovation Campuses and Susquehanna PPA
Pennsylvania, United States
2025
Under Construction1.9 GW

Amazon announced at least $20 billion of Pennsylvania investment to expand cloud computing infrastructure and AI innovation campuses, with Salem Township and Falls Township identified as the first communities. Pennsylvania officials describ

Elea Rio AI City
Rio de Janeiro, Rio de Janeiro, Brazil
2025
Under Construction1.5 GW

Elea Data Centers describes Rio AI City as a digital ecosystem in Rio de Janeiro's Olympic Park region for AI and cloud workloads across Latin America. Elea's official project page says the first phase starts with 1.5 GW of certified renewa

Vantage Frontier Shackelford County AI Campus
Shackelford County, Texas, United States
2025
Under Construction1.4 GW

Vantage Data Centers announced Frontier in August 2025 as a more than $25 billion mega-scale AI campus in Shackelford County, Texas. Vantage says the campus will provide 1.4 GW of GPU compute capacity, sit on 1,200 acres, include 10 data ce

Stargate Abilene AI Data Center Campus
Abilene, Abilene, Texas, United States
2025
Under Construction1.2 GW

Stargate Abilene is the flagship Stargate AI data center campus at the Lancium Clean Campus in Abilene, Texas. Crusoe says construction began in June 2024 and that the initial two-building, 200+ MW phase was expected to be energized in the

Meta El Paso AI Data Center
El Paso, El Paso, Texas, United States
2025
Under Construction1.0 GW

Meta announced El Paso, Texas as an AI-focused data center in October 2025 and updated the project in March 2026. Meta says the data center can scale to 1 GW and now will officially grow to 1 GW. The company increased the initial $1.5 billi

Meta Prometheus AI Supercluster (New Albany, Ohio)
New Albany, New Albany, Ohio, United States
2025
Under Construction1.0 GW

Meta's New Albany, Ohio data-center campus has been active in the community since 2017. Meta's official New Albany page supports more than $1.5 billion of data-center investment in Ohio, more than 300 operational jobs, and renewable-energy

Vantage Port Washington Lighthouse Stargate Campus
Port Washington, Port Washington, Wisconsin, United States
2025
Under Construction902 MW

Vantage Data Centers is developing the Port Washington Lighthouse campus in Wisconsin as a Stargate site for OpenAI and Oracle. Vantage's official location page says the 672-acre campus will include four single-story data centers totaling 9

Bell AI Fabric Data Center Network (British Columbia)
Kamloops & Merritt, British Columbia, Canada
2025
Under Construction500 MW

Bell Canada is developing the "Bell AI Fabric," a network of artificial intelligence data centers in British Columbia aimed at creating Canada's largest AI compute supercluster. The initiative targets a combined capacity of 500 megawatts (M

Applied Digital Polaris Forge 1 - Ellendale AI Factory
Ellendale, North Dakota, United States
2025
Under Construction400 MW

Applied Digital's Polaris Forge 1 campus in Ellendale, North Dakota is a staged AI factory campus for CoreWeave. Applied Digital first announced two approximately 15-year lease agreements to deliver 250 MW of critical IT load for CoreWeave

ByteDance — Thailand AI Data Hub
Bangkok, Bangkok / Chonburi, Thailand
2025
Under Construction400 MW

In June 2024, ByteDance (the parent company of TikTok) announced a massive $3.8 billion investment to establish a major data center and AI hub in Thailand. This initiative is designed to localize TikTok's content recommendation engines and

Vantage Nevada AI Data Center (NV1)
Henderson, Clark County, Nevada, United States
2025
Under Construction224 MW

Vantage Data Centers is developing its first hyperscale campus in Nevada, known as NV1, located in Henderson (Clark County). The 224-megawatt (MW) campus spans multiple buildings and is designed to meet the high-density power requirements o

SK Group-AWS Ulsan AI Data Center
Ulsan, Ulsan, South Korea
2025
Under Construction103 MW

SK Group and AWS announced a 15-year partnership to build a data center in Ulsan, South Korea for a new AWS AI Zone, with operations expected to begin in 2027. SK Group says it will lead construction while AWS establishes the AI Zone, bring

Khazna Ajman AI Data Center (UAE)
Ajman, Ajman, United Arab Emirates
2025
Under Construction100 MW

Khazna Data Centers is developing the UAE's first purpose-built AI campus in Ajman, delivering 100 megawatts of modular capacity across twenty 5 MW halls. Announced at GITEX 2024 and slated to open by the third quarter of 2025, the facility

Nebius–Mega Or National AI Data Center (Israel)
Modi'in, Modi'in, Israel
2025
Under Construction25 MW

Nebius and real estate developer Mega Or secured Israel's national tender to build a government-backed AI supercomputing hub in Modi'in outfitted with roughly 4,000 NVIDIA Blackwell GPUs. Supported by a $45 million grant from the Israel Inn

MTN AI Data Center (Nigeria)
Ikeja, Western Africa, Nigeria
2025
Under Construction9 MW

MTN Group has broken ground on a $240 million AI-ready campus in Ikeja, Lagos, designed to anchor the operator's new Genova infrastructure division. The modular build delivers 9 MW of IT capacity across two phases, with the initial 4.5 MW T

AWS Richmond County AI and Cloud Infrastructure Campus
Richmond County, North Carolina, United States
2025
Under Construction

Amazon announced an estimated $10 billion investment in Richmond County, North Carolina, to expand AWS data-center infrastructure for AI and cloud computing. State and county sources describe the project as an AI/cloud infrastructure campus

Cassava AI Data Center (South Africa)
Johannesburg, Southern Africa, South Africa
2025
Under Construction

Cassava Technologies is converting one of its Africa Data Centres sites in South Africa into the continent's first NVIDIA-backed "AI factory." Phase one installs 3,000 high-density GPUs by mid-2025 within the operator's Johannesburg footpri

Project Jupiter Dona Ana County AI Data Center
Dona Ana County, New Mexico, United States
2025
Under Construction

Project Jupiter is an AI data-center campus in Dona Ana County, New Mexico. OpenAI lists Dona Ana County as one of the Oracle/OpenAI Stargate sites announced in September 2025. Oracle's project page says the campus will include four data-ce

Stargate Lordstown Data Center (Ohio)
Lordstown, Lordstown, Ohio, United States
2025
Under Construction

OpenAI lists Lordstown, Ohio as one of the Stargate sites announced in September 2025. OpenAI says the Lordstown site is being developed through a SoftBank and OpenAI partnership and had broken ground on an advanced data-center design that

Stargate UAE Abu Dhabi AI Cluster Reference
Abu Dhabi, Abu Dhabi, United Arab Emirates
2025
Under Construction

Stargate UAE is a 1 GW AI compute cluster in Abu Dhabi inside the larger 5 GW UAE-US AI Campus. OpenAI says the cluster is the first international deployment of its Stargate AI infrastructure platform and that 200 MW is expected to go live

Meta Hyperion AI Data Center (Louisiana)
Rayville, Richland Parish, Louisiana, United States
2024
Under Construction5.0 GW

Meta's Richland Parish Data Center is the company's largest data center project to date in northeast Louisiana. Meta's own Richland Parish page describes a 4 million-square-foot site that will deliver over 2 GW of compute capacity to train

Microsoft Project Fairwater (Mount Pleasant, Wisconsin)
Mount Pleasant, Mount Pleasant, Wisconsin, United States
2024
Under Construction3.3 GW

Microsoft Fairwater is the company's Mount Pleasant, Wisconsin AI datacenter campus. Microsoft describes the first Fairwater facility as the world's most powerful AI datacenter, with hundreds of thousands of NVIDIA GPUs, closed-loop liquid

xAI Colossus / MACROHARDRR Greater Memphis AI Campus
Greater Memphis / Southaven xAI region, United States
2024
Under Construction2.0 GW

xAI describes Colossus as its gigafactory of compute, built rapidly and doubled to a 200,000 H100 GPU interconnected cluster, with a roadmap to 1 million GPUs. Mississippi state sources announced in January 2026 that xAI is locating the MAC

Google Cloud Malaysia AI Data Center (Johor Bahru)
Johor Bahru, Johor Bahru, Malaysia, Malaysia
2024
Under Construction220 MW

Google announced a $2 billion investment in Malaysia in 2024, its first data center and Google Cloud region in the country. Located in Johor Bahru — directly across the Strait of Johor from Singapore — the campus positions Google to serve S

Volcengine Inner Mongolia Horinger Computing Center
Horinger, Inner Mongolia, China
2024
Under Construction100 MW

DTDATA reports that the Volcengine Inner Mongolia Horinger Computing Center formally started construction in Horinger New Area in November 2024. The source says the project is being built in two phases: Phase 1 with eight data-center buildi

TikTok / ByteDance — Project Clover EU Data Center (Norway)
Hamar, Hamar, Norway
2024
Under Construction50 MW

Project Clover is TikTok's initiative to store European user data within European borders and segregate it from Chinese government access — responding to regulatory pressure from the European Commission, national data protection authorities

AWS Madison County Mississippi Data Center Complexes
Madison County, Mississippi, United States
2024
Under Construction

Amazon Web Services announced a $10 billion Madison County, Mississippi project in January 2024 to build two data-center complexes in two industrial parks, creating at least 1,000 jobs. Mississippi Development Authority repeats the same $10

Meta — Eagle Mountain, Utah AI Data Center Campus
Eagle Mountain, Utah, United States
2023
Under Construction500 MW

Meta's Eagle Mountain, Utah data center campus is a large-scale facility under development in Utah Valley, approximately 35 miles south of Salt Lake City. The site was selected for its access to renewable energy, land availability, and Utah

ByteDance — Johor AI Data Center
Kulai, Johor, Malaysia
Under Construction500 MW

ByteDance is developing a massive 500 MW data center campus in Kulai, Johor, to support its global AI research and TikTok workloads outside China. This project, part of a multi-billion dollar regional investment, is specifically engineered

Digital Edge — CGK AI Mega Campus
Bekasi, West Java, Indonesia
Under Construction500 MW

Digital Edge's CGK campus in Bekasi, Greater Jakarta, is a flagship 500 MW AI-ready infrastructure project, representing a $4.5 billion investment. The facility is designed to support the next generation of high-density AI workloads, featur

Hexagon Data Center — Riyadh
Riyadh, Riyadh, Saudi Arabia
Under Construction480 MW

The Hexagon Data Center in Riyadh is described as the world’s largest government-owned AI data center facility. Breaking ground in January 2026, the 480 MW campus is operated by the Saudi Data & AI Authority (SDAIA). It is a Tier IV designe

AirTrunk — TOK1 AI Expansion (Tokyo)
Inzai, Chiba, Japan
Under Construction300 MW

AirTrunk’s TOK1 campus in Inzai City, Chiba Prefecture — located in Tokyo’s eastern data center corridor — is undergoing a major 2026 expansion backed by a ¥180 billion (~$1.24 billion) green loan, the largest sustainability-linked data cen

Bulk Data Centers — N01 AI Campus
Kristiansand, Agder, Norway
Under Construction300 MW

The N01 Campus in Kristiansand, operated by Bulk Data Centers (Bulk Infrastructure Group), is one of Europe’s most strategically positioned hyperscale AI campuses — a purpose-built facility on the southwestern Norwegian coast that combines

Microsoft — Aragón AI Campus
Zaragoza, Aragón, Spain
Under Construction300 MW

Microsoft is building a 300 MW flagship AI data center campus in Zaragoza, Aragón, as part of its multi-billion euro investment in Spanish digital infrastructure. The facility is specifically engineered to host high-density AI workloads for

EcoDataCenter — Borlänge AI Mega Campus
Borlänge, Dalarna, Sweden
Under Construction250 MW

EcoDataCenter 2, located in Borlänge, Sweden, is a flagship AI expansion project built on the site of a former paper mill. With an initial capacity of 250 MW and scalability up to 600 MW, it is one of the largest AI-ready campuses in the No

Google — Skien AI Campus
Skien, Telemark, Norway
Under Construction240 MW

Google is developing a €600 million data center campus in Skien, Norway — the company's first major hyperscale investment in Norway and a significant expansion of Google's Northern European AI infrastructure footprint. The 240 MW facility i

Stargate Norway — Narvik AI Gigafactory
Narvik, Nordland, Norway
Under Construction230 MW

"Stargate Norway" is a $1 billion "AI Gigafactory" located in Kvandal, near Narvik. A strategic collaboration between OpenAI, Nscale, and Aker, the facility is designed to host 100,000 NVIDIA GPUs by late 2026. The site leverages Narvik's A

Meta — Montgomery AI Expansion
Montgomery, Alabama, United States
Under Construction227 MW

Meta is adding two massive buildings to its Montgomery, Alabama campus, bringing the total investment at the site to $1.5 billion. The expansion provides an additional 227 MW of clean-powered capacity, specifically optimized for high-densit

DC BLOX — Conyers AI Campus
Conyers, Georgia, United States
Under Construction216 MW

DC BLOX’s Conyers campus is a 216 MW facility (144 MW critical load) located east of Atlanta, Georgia. The first phase of the development is scheduled for delivery in 2026, specifically targeting the demand for AI-optimized colocation and h

Microsoft — Kemps Creek AI Campus (Sydney)
Sydney, New South Wales, Australia
Under Construction190 MW

Microsoft’s 190 MW hyperscale campus in Kemps Creek, Western Sydney, is a central component of its A$5 billion Australian infrastructure expansion. This facility is purpose-built to handle the massive compute requirements of Azure AI and Op

SINES 4.0 — SIN02 AI Gigafactory
Sines, Alentejo, Portugal
Under Construction180 MW

SINES 4.0 SIN02 is a massive 180 MW expansion of the Start Campus hyperscale site in Sines, Portugal. Evolving into an "AI Gigafactory," the facility is designed to host over 12,000 next-generation NVIDIA GPUs for large-scale AI model train

NEXTDC — M4 Melbourne 'AI Factory'
Melbourne, Victoria, Australia
Under Construction160 MW

NEXTDC’s M4 Melbourne is a $2 billion flagship "AI Factory" under construction in Fishermans Bend, Melbourne’s premier urban renewal precinct. With planned capacity of 150-162 MW across a purpose-built hyperscale campus, M4 represents Austr

ODATA — QR03 Querétaro AI Campus
El Marqués, Querétaro, Mexico
Under Construction150 MW

ODATA's QR03 campus in El Marqués, Querétaro, is set to be the largest single data center campus in Mexico with a capacity of 150 MW. Developed by ODATA (a subsidiary of Aligned Data Centers), the facility specifically targets the surging d

SoftBank — Sakai AI Data Center
Sakai, Osaka, Japan
Under Construction150 MW

SoftBank is building a 150 MW AI data center at the former Sharp LCD factory site in Sakai City, Osaka Prefecture, with completion targeted for late 2026. The facility is purpose-built to host NVIDIA Blackwell GPU systems (DGX B200 and GB20

EDGNEX — Jakarta AI Data Center
Jakarta, Jakarta, Indonesia
Under Construction144 MW

EDGNEX’s Jakarta facility is a 144 MW hyperscale data center specifically designed for high-density AI racks and generative AI workloads. Representing a $2.3 billion investment, the campus features advanced liquid cooling and modular infras

Viettel — Tan Phu Trung AI Data Center
Ho Chi Minh City, Ho Chi Minh City, Vietnam
Under Construction140 MW

Viettel's Tan Phu Trung facility is a massive 140 MW hyperscale data center located in Ho Chi Minh City’s Cu Chi district. Representing a significant expansion of Viettel’s digital infrastructure, the campus is designed to meet the growing

ODATA — BG03 Bogotá AI Campus
Bogotá, Cundinamarca, Colombia
Under Construction120 MW

ODATA's BG03, located in the Cundinamarca region near Bogotá, is set to be Colombia's largest data center with 120 MW of capacity. Part of a $1.3 billion regional expansion, the campus is specifically designed for high-density AI and hypers

Microsoft — Markham AI Megaproject
Markham, Ontario, Canada
Under Construction112 MW

Microsoft's Markham Megaproject, located on Langstaff Road, is a central pillar of the company's multi-billion dollar infrastructure expansion in Canada. With a planned capacity of 112 MW, the facility is specifically engineered to host hig

Khazna QAJ1 — Ajman AI Data Center
Ajman, Ajman, United Arab Emirates
Under Construction100 MW

Khazna QAJ1 is a 100 MW AI-optimized data center under construction in Ajman and positioned by Khazna as the first purpose-built AI data center in the UAE and wider region. Khazna's October 2024 launch announcement described a 100,000-squar

Microsoft — Poland AI Expansion (Warsaw)
Warsaw, Masovian, Poland
Under Construction100 MW

Microsoft is investing $700 million to expand its hyperscale cloud region near Warsaw, with a target completion date of mid-2026. This expansion focuses on increasing high-performance AI compute capacity for enterprise and public sector use

Nvidia & Foxconn — Kaohsiung AI Factory
Kaohsiung, Kaohsiung, Taiwan
Under Construction100 MW

The Nvidia-Foxconn AI Factory in Kaohsiung is Taiwan's largest advanced AI supercomputing center, scheduled to become operational in the first half of 2026. Representing a $1.4 billion investment, the facility is the first in Asia to deploy

eStruxture's CAL-3 Hyperscale Data Center (Calgary)
Balzac, Western Canada, Canada
Under Construction90 MW

In October 2024, Montreal-based eStruxture Data Centres announced plans for CAL-3, a 90 MW hyperscale data center north of Calgary in Rocky View County. Slated to go live in the second half of 2026, CAL-3 will be Alberta's largest and most

Nebius & Mega Or — Israel AI Hub
Beit Shemesh, Central District, Israel
Under Construction80 MW

The Nebius & Mega Or Israel AI Hub is an 80 MW combined development across sites in Beit Shemesh and Masmiyya. Representing an $880 million investment, the facility is specifically designed for high-density GPU workloads, utilizing liquid-c

Sberbank — Balakovo AI Data Center
Balakovo, Saratov Oblast, Russia
Under Construction50 MW

Sberbank’s Balakovo facility is a massive regional AI data center located in the Saratov region. Featuring 7 modules and 3,500 server racks, the site has an estimated capacity of approximately 50 MW. Each rack is engineered to support high-

NVIDIA AI Factory — Helsinki, Finland
Helsinki, Uusimaa, Finland
Under Construction40 MW

NVIDIA and CSC — Finland's IT Center for Science — announced a joint AI Factory in Helsinki as part of NVIDIA's European Sovereign AI initiative. The facility will be powered by 100% hydroelectric power sourced from Nordic renewable energy

Yandex — Vladimir AI Data Center
Vladimir, Vladimir Oblast, Russia
Under Construction40 MW

Yandex is developing its sixth data center in Vladimir Oblast, approximately 190 km east of Moscow, with capacity exceeding 40 MW and targeted for 2026 completion. The facility forms part of Yandex’s continuous data center expansion program

Yondr — Toronto AI Data Center
Toronto, Ontario, Canada
Under Construction27 MW

Yondr's Toronto data center is a 27 MW facility that broke ground in January 2025, with a scheduled "Ready for Service" (RFS) date in mid-2026. The project is notable for its AI-ready design, featuring a waterless closed-loop cooling system

Equinix — SG6 Singapore AI Data Center
Singapore, Jurong, Singapore
Under Construction20 MW

Equinix SG6 is a nine-story, "AI-ready" data center located in Singapore’s Jurong area, scheduled to open in Q1 2027. Representing a $260 million investment, the 20 MW facility is specifically engineered to host high-density AI and machine

Microsoft — Greece AI Region (Athens)
Spata, Attica, Greece
Under Construction20 MW

Microsoft is developing its first hyperscale data center region in Greece, consisting of three sites in the Eastern Attica area (Spata and Koropi). The flagship ATH04 facility in Spata has a confirmed IT capacity of 19.2 MW and is specifica

DataVolt — Tashkent AI Data Center
Tashkent, Tashkent, Uzbekistan
Under Construction12 MW

DataVolt’s Tashkent facility is a $150 million "green" data center scheduled for completion by the end of 2026. With an initial capacity of 12 MW, it is designed to be the first in Central Asia specifically optimized for high-density AI wor